Sutton Pond

Sutton Pond

Scope:Designed as a water source for the Ravenna development, this pond required 450,000 cubic yards of cut to fill. HEI Civil performed this work as a subcontractor to AUI and they required the project had to be completed in 30 calendar days. In order to complete the 450,000 CY of excavation and embankment on schedule, HEI was required to move almost 20,000 CY per day. Adding to the challenge, rippable rock was found in the reservoir bottom. Excavating was able to meet the challenges and completed the project on time.

Comments are closed.